40 men can finish a work in 25 days. In how many days, 25 men will finish the same work?
Answer: 40 days
Explanation
40 men finish the work in 25 days
Total work = 40 men * 25 days = 1000 man-days
Now, 25 men will finish the work:
1000 man-days / 25 men = 40 days
This question appeared in
Past Papers (4 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (1 times)
Inspector Customs, Intelligence Officer Past Papers, Syllabus (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work in ______ days if they work together.
- A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.
- A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work?
- A can finish a work in 40 days. 5 is 255% less efficient then A. The number of days A & B will take to finish the work working together in nearly ≠ 3?
- 30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
- A and B can together finish a work in 30 days. They worked together for 20 days and then B left after 20 days. A finished the worked. In how many days A alone can finish the work?
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- 250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?
- A is 4 times as fast as B and therefore is able to finish the work in 45 days less than B. A and B, can complete the work in how many days?