A and B can together finish a work in 30 days. They worked together for 20 days and then B left after 20 days. A finished the worked. In how many days A alone can finish the work?

Answer: 60
Explanation

Amount of work done by A and B in 1 day = 1/30

Amount of work done by A and B in 20 days = 20 × (1/30) = 20/30 = 2/3

Remaining work – 1 – 2/3 = 1/3

A completes 1/3 work in 20 days

Amount of work A can do in 1 day = (1/3)/20 = 1/60

=> A can complete the work in 60 days