P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
Answer: 12
Explanation
Work done by P in 1 day = 1/15
Work done by Q in 1 day = 1/10
Work done by P and Q in 1 day = 1/15 + 1/10 = 1/6
Work done by P and Q in 2 days = 2 × (1/6) = 1/3
Remaining work = 1 – 1/3 = 2/3
Time taken by P to complete the remaining work 2/3 = (2/3) / (1/15) = 10 days
Total time taken = 2 + 10 = 12 days
This question appeared in
Past Papers (2 times)
BISP Past Papers and Syllabus (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days, ten adults left and four children joined them. How many days will they take to complete the remaining work?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?