A is 4 times as fast as B and therefore is able to finish the work in 45 days less than B. A and B, can complete the work in how many days?

Answer: 12 days
Explanation

A is 4 times as fast as B, so A's rate of work is 4 times B's rate of work.

Since A finishes the work in 45 days less than B, let's assume B takes x days to finish the work. Then A takes x - 45 days to finish the work.

Since A is 4 times as fast as B, A's rate of work is 4 times B's rate of work. So, A's time to finish the work is 1/4 of B's time.

We can set up an equation based on the above: x - 45 = (1/4)x

Solve for x: x - 45 = (1/4)x --> 4x - 180 = x --> 3x = 180 --> x = 60

So B takes 60 days to finish the work, and A takes 60 - 45 = 15 days to finish the work.

Since A and B work together, their combined rate of work is the sum of their individual rates. Let's find their individual rates.

B's rate = 1/60 (work done per day)

 A's rate = 1/15 (work done per day)

Combined rate = (1/60 + 1/15) = (1/60 + 4/60) = 5/60 = 1/12

So A and B together can complete the work in 12 days.

This question appeared in Past Papers (5 times)
This question appeared in Subjects (1 times)
MATHS MCQS (1 times)

Install this app on your device for quick access right from your home screen.