30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.

Answer: 21
Explanation

Let the required number of labourers be x

Less working hour/day, More labours (Indirect proportion)

More days, fewer labourers (Indirect proportion)