30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
Answer: 21
Explanation
Let the required number of labourers be x
Less working hour/day, More labours (Indirect proportion)
More days, fewer labourers (Indirect proportion)
This question appeared in
Past Papers (7 times)
Pakistan Navy Past Papers & Jobs (7 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (1 times)
VERBAL & NON VERBAL INTELLIGENCE TEST MCQS PDF (1 times)
Related MCQs
- 250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
- 195 men working 10 hours a day can finish a job in 20 days. How many men will be employed to finish the same job in 15 days if they work 13 hours a day?
- Twelve men take 6 hours to finish a piece of work. After the 12 men have worked for 1 hour, the contractor decides to call in 8 more men. How many more hours would 20 men take to complete the remaining work?
- 125 people can finish a piece of work in 120 days , find the no. of people required to finish this same work in 100 days .
- A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work?
- A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.
- A can finish a work in 40 days. 5 is 255% less efficient then A. The number of days A & B will take to finish the work working together in nearly ≠ 3?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?