If 3 persons do 3 times of a particular work in 3 days, then 7 persons can do 7 times of that work in _________.
Answer: 3 days
Explanation
3 persons can do 3 jobs in 3 days
1/3 of the work will take 1/3 of the time, so
3 people can do 1 job in 1 day
It will take 1 person 3 times as long, so
1 person can do 1 job in 3 days
7 persons can do 7 times the work in the same time, so
7 persons can do 7 jobs in 3 days
This question appeared in
Past Papers (7 times)
Pakistan Navy Past Papers & Jobs (7 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (1 times)
VERBAL & NON VERBAL INTELLIGENCE TEST MCQS PDF (1 times)
Related MCQs
- 39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work?
- A is 4 times as fast as B and therefore is able to finish the work in 45 days less than B. A and B, can complete the work in how many days?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- A contractor estimates that 3 persons could rewire Jamal's house in 4 days. If he uses 4 persons instead of three, how long should they take to complete the job?
- Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?
- If 10 persons can do a job in 20 days than 20 persons with twice efficiency can do the same job in ____?