A contractor estimates that 3 persons could rewire Jamal's house in 4 days. If he uses 4 persons instead of three, how long should they take to complete the job?
Answer: 3 days
Explanation
Work = Persons × Days = 3 × 4 = 12 person-days
With 4 persons: 12 ÷ 4 = 3 days.
This question appeared in
Past Papers (6 times)
IBA STS 25 Years Past Papers Subject Wise (Solved) (2 times)
IBA STS Past Papers, Syllabus, Jobs (2 times)
JEST Past Papers (2 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- 39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work?
- If 10 persons can do a job in 20 days than 20 persons with twice efficiency can do the same job in ____?
- A bag of 20 kg of rice is consumed by 10 persons in 15 days. If 5 persons are added then the same rice shall be banished in?
- 14 persons earn Rs. 400 in 10 days. How many persons are required to earn Rs. 600.
- A prize of Rs. 240 is divided between two persons. If one person receives Rs. 180, then what is the difference between the amount received by the two persons?
- If 3 persons do 3 times of a particular work in 3 days, then 7 persons can do 7 times of that work in _________.
- If 30 persons can consume 20 kg of flour in 25 days. How much of the flour will 15 persons consume in 30 days?
- According to Section 99(3) of The Punjab Tenancy Act, 1887, the order of the _____________ on any such reference shall be conclusive as against persons who are not parties to the suits as well as against persons who are parties thereto.
- In a library, 11 persons arranged 319 books in 4 hours. How many persons are required to arrange 725 books in 5 hours?
- If a family of 9 persons spend Rs. 4800 in 8 months, how much will be spent by a family of 24 persons in 16 months?