120 men are used to build huge building for 30 days. How long will it take 80 men to do the same work?

Answer: 45 days
Explanation

120 men can do work = 30 days

1 man can do this work = 120 x 30 = 3600 days

80 men can do this work = 3600/80 = 45 days