A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
Explanation
Given:
Time taken by A and B to complete the work = 12 days
Time taken by B and C to complete the work = 8 days
Time taken by C and A to complete the work = 6
Formulae used:
Time = Total work / Efficiency
Calculation:
Let us assume the total work is 1 unit.
⇒ A and B complete 1 unit work in 12 days → (A and B)'s 1 day's work = 1/12
⇒ B and C complete 1 unit work in 8 days → (B and C)'s 1 day's work = 1/8
⇒ A and C complete 1 unit work in 6 days → (A and C)'s 1 day's work = 1/6
Adding everyone's 1 day's work:
⇒2(A+B+C)=(1/12)+(1/8)+(1/6)
⇒A+B+C=9/48
= A, B, and C's 1 day's work = 9/48
⇒ B's 1 day's work = (A+B+C)−(A+C)
⇒ B's 1 day's work =(9/48)−(1/6) = 9-8 x/48 = 1/ 48
⇒ B completes 1/48 of the work in 1 day.
Therefore, B alone will take 48 days to complete the work.
Related MCQs
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?
- 30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.