A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
Answer: 1 day
Explanation
35 men completed the remaining job in 12 days.
Now the same job has to be done by 30 men.
We know that, M1D1=M2D2
Required time =3035×12=14 days
Delayed time =(14−13)=1 day
This question appeared in
Past Papers (3 times)
FIA Inspector Past Papers (1 times)
FIA Past Papers (1 times)
FPSC Past Papers (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are:
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- Hamza can do a work in 15 days and Aslam in 12 days. If they work on it together for 4 days, the fraction of work that is left is________?
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- A and B can together finish a work in 30 days. They worked together for 20 days and then B left after 20 days. A finished the worked. In how many days A alone can finish the work?
- 195 men working 10 hours a day can finish a job in 20 days. How many men will be employed to finish the same job in 15 days if they work 13 hours a day?
- A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days then that numbers of days taken by A B and C together to finish the work are?