If 10 people complete work in 20 days, in how many days can 8 people complete the same work?
Answer: 25 days
Explanation
10 men can complete the work in 20 days.This means the total work is:
10 men × 20 days = 200 man-days
Now, if 8 men work at the same rate:
200 man-days ÷ 8 men = 25 days
This question appeared in
Past Papers (8 times)
FIA Inspector Past Papers (1 times)
Pakistan Rangers Past Papers (1 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Past Papers (1 times)
PPSC PHP ASI Past Papers and Syllabus (1 times)
PPSC Punjab Police ASI Past Papers and Syllabus (2 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in _______ days.
- 6 person completes a work in 16 days, 8 people will complete the job in how many days.
- Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work_____?
- If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?
- A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in ____?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.