The bridge is completed in 20 days by 80 men. How long will it take 70 men to complete the work?

Answer: 23 days
Explanation

If 80 people complete the bridge in 20 days, then the total man-days required to complete the bridge is 80 people * 20 days = 1600 man-days.

Rounding up to the nearest whole number, 70 people will take approximately 23 days to complete the bridge