In independent projects evaluation, results of internal rate of return and net present value lead to
Answer: same decisions
Explanation
In independent projects evaluation, results of internal rate of return and net present value lead to cost decision. An Independent Project Evaluation is the evaluation of an individual project designed to achieve specific objectives within specified resources, in an adopted time span and following an established plan of action, often within the framework of a broader programme.
This question appeared in
Past Papers (1 times)
OTS Past Papers (1 times)
This question appeared in
Subjects (1 times)
ACCOUNTING (1 times)
Related MCQs
- Criterion for IRR (Internal Rate of Return)?
- A project should be accepted if its internal rate of return exceeds _____?
- When the coupon rate is less than the required rate of return the discount on the bond ______ as maturity approaches.
- Project invisibility can lead to sub-optimal results when ______ is used for capital retaining.
- What should a company do if the IRR is less than the required rate of return?
- Which of the following is a method used for evaluating the profitability of an investment by finding the interest rate that equates the present value of cash inflows with the present value of outflows?
- What is the impact of a higher required rate of return on IRR?
- An IRR greater than the required rate of return indicates ____?
- My results will lead _____ future research _____ the topic.
- According to the capital--asset pricing model (CAPM), a security's expected (required) return is equal to the risk free rate plus a premium: