16 men dig a ditch in 10 days. the number of men required to complete the job in half the time is --.
Answer: 32
Explanation
32 men's needed to complete the work in half the time
***
ND18-1-2023
This question appeared in
Past Papers (5 times)
ASF Inspector Past Papers (1 times)
ASF Past Papers (1 times)
FPSC 5 Years Past Papers Subject Wise (Solved With Details) (1 times)
FPSC Past Papers (1 times)
IBA STS Past Papers, Syllabus, Jobs (1 times)
This question appeared in
Subjects (1 times)
MATHS MCQS (1 times)
Related MCQs
- 12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
- If 16 workers can complete a task in 40 days. The number of workers is required to complete task in 80 days is?
- If 25 workers can complete a task in 30 days. The number of workers is required to complete the task in 15 days is?
- If 9 person can finish a task in 5 days, then how many people are required to complete the same task in 3 days?
- Two classrooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 days. If the number of workers is increased up to 10, how many days will be taken in the completion of work?
- Alia can complete an assignemnt in 5 days and Babar can complete the same assignment is 20 days. The time taken by both Alia and Babar to complete the assignment working together is:
- Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
- If six people dig a well 200m deep in 15 days, the number of people that are required to dig the same well in 18 days is _____?
- Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
- 120 men can do a work in 90 days,how many more men required to complete the same work in 40 days?