If 4 men can color 48m cloth in 2 days, 6 men can color 36 m cloth in __________.

If 4 men can color 48m cloth in 2 days, 6 men can color 36 m cloth in __________.

Explanation

The length of cloth painted by one man in one day = 48 / 4 x 2 = 6 m 

No. of days required to paint 36 m cloth by 6 men = 36 / 6 x 6 = 1 day