12 men can work in 24 days how can doing the 8 men same work on which days?
12 men can work in 24 days how can doing the 8 men same work on which days?
Explanation
If 12 men can complete the work in 24 days,
it means that the total number of man-days required to complete the work is:
12 men * 24 days = 288 man-days.
288 man-days / 8 men = 36 days.