If 9 person can finish a task in 5 days, then how many people are required to complete the same task in 3 days?

If 9 person can finish a task in 5 days, then how many people are required to complete the same task in 3 days?

Explanation

If 9 person can finish a task in 5 days, then 15 people are required to complete the same task in 3 days.

X y = task X=9 Y=5 X*y=9*5=45 Now days=y=3 3*x=45 X=45/3 X=15 daya