If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day?
Answer: 15
Explanation
Here M1 = 30, D1 = 16,
T1 = 9, M2 = 36 and T2 = 8
By formula, M1D1T1 = M2D2T2
30 x 16 x 9 = 36 x D2 x 8
∴ D2 = (30 x 16 x 9)/(36 x 8) = 15 days
This question appeared in
Past Papers (7 times)
Junior Clerk Past Papers (1 times)
PPSC 5 Years Past Papers Subject Wise (Solved with Details) (2 times)
PPSC Intelligence Officer Past Papers & Syllabus (1 times)
PPSC Junior Clerk Past Papers and Syllabus (1 times)
PPSC Past Papers (2 times)
This question appeared in
Subjects (2 times)
MATHS MCQS (2 times)
Related MCQs
- 12 men and 15 women can reap a field in 14 days. Find the number of days that 7 men and 5 women will take to reap it?
- 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job, and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
- 39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work?
- 250 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is ______?
- A completes a work in 12 days. B completes the same work in 15 days. A started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
- Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly completely the work in?
- Five men can prepare ten toys in six days working six hours a day. Then in how many days can twelve men prepare sixteen toys working eight hours a day?
- If a person A completes a work in 12 days and person B in 6 days and they start working together then In how many days they will complete the work?
- 24 workers working 7 hours a day produce 4000 units in 30 days. In how many days 30 workers working 8 hours a day will produce 3500 units?
- If 15 workers can paint a certain number of houses in 24 days, how many days will 40 workers take, working at the same rate, to do the same job?