If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?

If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?

Explanation

To solve this problem, we can use the concept of man-days:

8 people × 60 days = 480 man-days

Since the amount of work remains the same, we can set up an equation for 6 people:

6 people × x days = 480 man-days

To find the number of days, divide 480 by 6:

x = 480 ÷ 6

x = 80 days