If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?
If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?
Explanation
10 workers make 10 tables in 10 days.1 worker makes 1 table in 10 days.
Similarly, 5 workers can make 5 tables in 10 days.