Let's denote A's rate of work as A, and B's rate of work as B.

Given A + B together complete the work in 12 days:

(A + B)'s 1 day's work = 1/12

B alone completes the work in 20 days:

B's 1 day's work = 1/20

A's 1 day's work = (A + B)'s 1 day's work - B's 1 day's work

= 1/12 - 1/20

= (5 - 3) / 60

= 2 / 60

= 1 / 30