10 men can complete a job in 14 days. How long will it take 4 men to finish the same job if the same at the same rate?

10 men can complete a job in 14 days. How long will it take 4 men to finish the same job if the same at the same rate?

Explanation

10 men complete a job in 14 days, so the total work equals 10 men × 14 days.

With 4 men, the work remains the same, but takes longer.

Multiply the original duration by the ratio of men: 14 days × (10/4) = 35 days.

Therefore, 4 men take 35 days to finish the job at the same rate.