A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

Explanation

Given:

Time taken by A and B to complete the work = 12 days

Time taken by B and C to complete the work = 8 days

Time taken by C and A to complete the work = 6  days

Formulae used:

Time = Total work / Efficiency

Calculation:

Let us assume the total work is 1 unit.

A and B complete 1 unit work in 12 days (A and B)'s 1 day's work = 1/12

B and C complete 1 unit work in 8 days (B and C)'s 1 day's work = 1/8

A and C complete 1 unit work in 6 days (A and C)'s 1 day's work = 1/6

Adding everyone's 1 day's work:

= A, B, and C's 1 day's work = 9/48


B's 1 day's work =

B's 1 day's work =(9/48)

B completes 1/48 of the work in 1 day.

Therefore, B alone will take 48 days to complete the work.